Contents

EXECUTIVE SUMMARY 1

1.    Introduction  2

1.1   Background  2

1.2   Scope of the EM&A Report  2

1.3   Organisation Structure  2

1.4   Summary of Construction Programme and Activities  3

1.5   Summary of EM&A Programme Requirements  3

1.6   Status of Other Statutory Environmental Requirements  4

2.    EM&A Results  5

2.1   Environmental Site Inspection  5

2.2   Waste Management Status  5

2.3   Implementation Status of the Environmental Protection Requirements  5

2.4   Summary of exceedance of the Environmental Quality Performance Limit  6

2.5   Summary of Environmental Non-compliance, environmental complaint, Notification of summons and successful prosecution  6

3.    Upcoming works for the next reporting period  7

3.1   Construction activities for the next reporting period  7

4.    Conclusion  8

Appendix A  Location of the cable jointing works at Upper cheung sha beach

Appendix B  Project organisation

Appendix C  waste flow table

Appendix D  Summary of Implementation SCHEDULE AND STATUS of environemental mitigation measures for THE INSTALLATION OF SUBMARINE CABLE

Appendix E  CUMULATIVE STATISTICS ON EXCEEDANCES, environmental complaint, environmental summon and prosecution log

 

List of Tables

Table 1.1      summary of construction programme  3

Table 1.2      Summary of status for the EM&A PRogramme under the Updated EM&A Manual and FEP-02/429/2012/B  3

Table 1.3      Summary of the status of valid environmental licence, notification, permit and documentations  4

Table 2.1      key findings and recommendations from site inspections and contractor’s follow-up actions  5

Table 2.2      Quantities of waste generated under FEP-02/429/2012/B  5

 

 

 


EXECUTIVE SUMMARY

The associated works for cable jointing at the land section at Upper Cheung Sha Beach (UCSB) for the Development of the Integrated Waste Management Facilities Phase 1, under Further Environmental Permit (FEP-02/429/2012/B), commenced on 17 February 2025, and all construction works were completed on 31 March 2025. All marine-based works were completed on 20 December 2023. As there were no marine works related to the cable jointing at UCSB, water quality monitoring and marine mammal exclusion zone monitoring are not required.

This is the 5th monthly Environmental Monitoring and Audit (EM&A) report, presenting the EM&A activities carried out during the period from 17 March 2025 to 31 March 2025, in accordance with the approved Updated EM&A Manual and FEP-02/429/2012/B.

Summary of the construction activities undertaken during the reporting period

The major construction activities undertaken during the reporting period include:

Land-based Works

·        Cable Jointing Work

·        Site Protection and Reinstatement

·        Site clearance

Environmental Site Inspection

Joint weekly site inspections were conducted by representatives of the Contractor, CLP, and the Environmental Team (ET) on 20 and 27 March 2025. The representative of the IEC participated in the site inspections on 20 March 2025. Details of the audit findings are presented in Section 2.1.

Environmental Exceedance / Non-conformance / Complaint / Summons and Prosecution

No non-compliance event was recorded during the reporting period.

No environmental complaint was received during the reporting period. The cumulative environmental complaint log is presented in Appendix E.

No summon/ successful prosecution was received during the reporting period.

reporting changes

There was no reporting change in the reporting period.

future key issues and Upcoming works for the next reporting period

All the construction works of the Project were completed on 31 March 2025. The EM&A programme during construction phase was terminated on the same day of completion.


 

1.         Introduction

1.1       Background

The Environmental Protection Department (EPD) of the Government of the Hong Kong Special Administrative Region (HKSAR) proposed to construct the Integrated Waste Management Facilities (IWMF) Phase 1 on an artificial island near Shek Kwu Chau, south of Lantau Island for the purpose of treating municipal solid waste and generating electricity from the waste treatment process for its own use and export surplus electricity, if any, to the power grid.

The EIA Report (EIA-201/2011) was approved by the EPD on 17 January 2012 with the Environmental Permit (EP) of the Project issued on 19 January 2012 (EP-429/2012) and a variation of the EP on 14 October 2016 (EP-429/2012/A).  A Further EP (FEP-01/429/2012/A) was granted to Keppel Seghers-Zhen Hua Joint Venture for the reclamation works and construction of the IWMF on 27 December 2017.  Another latest Further EP (FEP-02/429/2012/B) was granted to CLP Power for the installation of the 132kV submarine cable circuits connecting Cheung Sha, South Lantau and Shek Kwu Chau Artificial Island on 25 May 2020.  The proposed cable would land at the landing portal at Upper Cheung Sha Beach (UCSB).  An Environmental Review Report (ERR) was prepared and approved to support the application of FEP-02/429/2012/B.

The Environmental Monitoring and Audit (EM&A) programme during the cable construction of the Project has been performed during the reporting period in accordance with the relevant EM&A requirements stipulated in the Updated EM&A Manual under FEP-02/429/2012/B. The construction of the cable jointing at the land section at UCSB commenced on 17 February 2025. The location of the cable jointing works is shown in Appendix A.

ERM-Hong Kong Limited (ERM) was appointed by the Permit Holder, CLP Power Hong Kong Limited (CLP Power) to undertake the Environmental Monitoring and Audit (EM&A) programme during the cable jointing at the land section of the submarine cable for the Development of the Integrated Waste Management Facilities Phase 1 (hereafter referred as the “Project”).

All marine-based works were completed on 20 December 2023. As there are no marine works related to the cable jointing at Upper Cheung Sha Beach, water quality monitoring and marine mammal exclusion zone monitoring are not required.

All construction works of the Project were completed on 31 March 2025. The EM&A programme for construction phase was completed on the same day.

1.2       Scope of the EM&A Report

This is the 5th EM&A report which summarizes the key findings of the EM&A programme during the reporting period from 17 March 2025 to 31 March 2025 for the construction works in accordance with the Updated EM&A Manual and the requirements of FEP-02/429/2012/B.

1.3       Organisation Structure

The organization structure for the construction works under FEP-02/429/2012/B and contact details are shown in Appendix B.

1.4       Summary of Construction Programme and Activities

A summary of the construction programme is presented in Table 1.1.

Table 1.1  summary of construction programme

Construction Works

Period

Excavation work and erect Joint Bay scaffolding

17 Feb 2025 to 22 Feb 2025

Cable jointing work

24 Feb 2025 to 19 Mar 2025

Protection and reinstatement work

20 Mar 205 to 31 Mar 2025

Site clearance

31 Mar 2025

Note: Due to the humid weather at the beginning of March, the construction programme was delayed by two weeks.

A summary of major construction activities undertaken during the reporting period include:

Land-based Works

·        Cable Jointing Work

·        Site Protection and Reinstatement

·        Site clearance

1.5       Summary of EM&A Programme Requirements

A summary of the status of EM&A Programme for all environmental aspects required under the Updated EM&A Manual and FEP-02/429/2012/B are presented in Table 1.2.  The requirements of relevant environmental monitoring, including monitoring parameters, Action and Limit Levels, Event and Action Plan(s), environmental mitigation measures, etc. are presented in Section 2.

Table 1.2  Summary of status for the EM&A PRogramme under the Updated EM&A Manual and FEP-02/429/2012/B

EM&A Programme Requirements

Status

Environmental Site Inspection

Regular Site Inspection

Completed on 31 March 2025.

Water Quality

Baseline Monitoring

Completed. The Baseline Water Quality Monitoring Report was submitted on 24 August 2023 and EPD’s approval was obtained on 19 October 2023.

Construction Phase Monitoring

Completed on 16 December 2023.

Post-Project Monitoring

Completed. The Post Project Monitoring Report was submitted on 21 February 2024 and EPD’s no comment was obtained on 19 March 2024.

Ecology

Marine Mammal Exclusion Zone Monitoring

Completed. Submarine cable installation using vessel and jetting machine was completed on 27 November 2023, and Marine Mammal Exclusion Zone Monitoring ended on the same day.

 

1.6       Status of Other Statutory Environmental Requirements

A summary of the valid permits, licences, and/or notifications on environmental protection for the Project is presented in Table 1.3.

Table 1.3  Summary of the status of valid environmental licence, notification, permit and documentations

Permit/ Licences/ Notificaiton

Reference No.

Validity Period

Remarks

Environmental Permit

EP-429/2012/A

Throughout the Contract

Permit granted on 19 January 2012

Further Environmental Permit

FEP-02/429/2012/B

Throughout the Contract

Permit granted on 17 January 2020

Construction Noise Permit

GW-RS0075-25

3 February 2025 – 30 April 2025

-

Billing Account for Disposal of Construction Waste

7052906

Throughout the Contract

-


 

2.         EM&A Results

2.1       Environmental Site Inspection

Joint weekly site inspections were conducted by representatives of the Contractor, CLP and ET on 20 and 27 March 2025 at the landing point at UCSB.  The representative of Independent Environmental Checker (IEC) joined the site inspection on 20 March 2025.  No non-compliance was recorded during the site inspections.  Key findings and recommendations for the site inspections in this reporting month are summarized in Table 2.1.

Table 2.1  key findings and recommendations from site inspections and contractor’s follow-up actions

Site Inspection Date

Findings and recommendations

Contractor’s Follow-up Action(s) Taken

20 March 2025

There was no major observation during the site inspection.

N/A

27 March 2025

There was no major observation during the site inspection.

N/A

 

All follow-up actions requested by ET during the site inspections were undertaken as reported by the Contractor.

2.2       Waste Management Status

The quantities of different types of waste generated are summarized in Table 2.2.  The excavated sand material will be backfilled on site.  No waste was generated during the reporting period. Detailed waste flow table is presented in Appendix C.

Table 2.2  Quantities of waste generated under FEP-02/429/2012/B

Reporting Period

Quantity

Inert C&D Materials (in ‘000 kg)

Non-inert C&D Materials

Chemical Waste (in ‘000 kg3

General Refuse

(in ‘000 kg)

Recycled Materials

Paper/ Cardboard Packaging (in ‘000 kg3)

Plastics

(in ‘000 kg3)

Metals (in ‘000 kg3)

17 Mar 2025 – 31 Mar 2025

4.53

0

0

0

0

0

 

2.3       Implementation Status of the Environmental Protection Requirements

The Contractor has implemented all the environmental mitigation measures and requirements as stated in the approved EIA Report, ERR, approved Updated EM&A Manual and FEP-02/429/2012/B.  The implementation status of the environmental mitigation measures during the reporting period is summarized in Appendix D

2.4       Summary of exceedance of the Environmental Quality Performance Limit

No water quality monitoring and marine mammal exclusion zone monitoring was conducted during the reporting period.

Cumulative statistics on exceedance is provided in Appendix E.

2.5       Summary of Environmental Non-compliance, environmental complaint, Notification of summons and successful prosecution

No non-compliance event was recorded during the reporting period.

No environmental complaint was received during the reporting period. 

The cumulative environmental complaint log is presented in Appendix E.

No summons/ successful prosecution was received during the reporting period.  The cumulative summon/ prosecution log is presented in Appendix E.


 

3.         Upcoming works for the next reporting period

3.1       Construction activities for the next reporting period

All the construction works of the Project were completed on 31 March 2025, and the site was handed back to Leisure and Cultural Services Department (LCSD) on the same date. Site photo taken on 31 March 2025 can be found in Figure 1. No construction works will be conducted in the upcoming month.

Figure 1   Photo taken at Cable jointing work site on 31 March 2025

A sandy beach with trees in the background

AI-generated content may be incorrect.


 

4.         Conclusion

All the construction works of the Project were completed on 31 March 2025. This is the 5th Monthly EM&A Report presenting the key findings of the EM&A works undertaken during the reporting period from 17 March 2025 to 31 March 2025 in accordance with the approved Updated EM&A Manual and the requirements of Further Environmental Permit FEP-02/429/2012/B.  Weekly environmental site inspections of the construction works and audit of the implementation of environmental mitigation measures were conducted by the ET during the reporting period.

There were no non-compliance event, environmental complaint and summon/ successful prosecution recorded during the reporting period.

The Contractor had implemented possible and feasible mitigation measures to mitigate the potential environmental impacts.  The ET had kept track of the EM&A programme to ensure compliance of environmental requirements and the proper implementation of all necessary mitigation measures.